AUQ: Additional Finance Facility for Wash-hi Majaza Project
ALARA RESOURCES LIMITED
- Al Hadeetha Resources has secured an additional ~USD15 million loan from Sohar Bank International for the Al Wash-hi Majaza Copper-Gold Project development.
- Civil construction of the project's 1MTPA copper processing plant is approximately three quarters complete, with substantial progress in MEP works.
- Project commissioning phase is expected to commence from August 2023, with commercial production commencement targeted for 27 September 2023.
2023-05-02 09:33:00