IPL: Gas supply update for Phosphate Hill plant
INCITEC PIVOT LIMITED
- Incitec Pivot Limited (IPL) has been notified by its gas supplier, Power and Water Corporation (PWC), of a reserves shortfall under the gas supply agreement for IPL's Phosphate Hill plant.
- The additional cost of sourcing shortfall gas for the remainder of FY23 is expected to be $15m-$20m, bringing the total FY23 EBIT impact to $75m-$90m.
- PWC indicates that the reserve shortfalls are expected to be ongoing beyond FY23 for the remainder of the term of the Gas Supply Agreement, which lasts until mid-2028.
2023-06-06 15:25:00