HE8: Flowback Update on Presidio 52 No.1 Well

HELIOS ENERGY LTD

2023-05-16 10:04:00

HE8: Update on Presidio 52 No.1 Well

HELIOS ENERGY LTD

2023-05-15 08:27:00

HE8: Update of Presidio 52 No.1 Well

HELIOS ENERGY LTD

2023-02-09 15:06:00

HE8: Update - Presidio 52 No.1 Well Completion

HELIOS ENERGY LTD

  1. The Frack Job for Presidio Well 52#1 is expected to commence on 10 January 2023.
  2. To date, three water storage facilities have been completed and filled with water, frack tanks and six sand silos are on site and have also been functionally tested.
  3. Helios will execute a four-stage vertical frack across the 1,623 feet interval between the lower bench of the Ojinaga Formation and the bottom of the casing including Eagle Ford and Boquillas.

2023-01-06 08:19:00